Timeline

STAGE 1 - LAND PURCHASE:
LAND PURCHASED - APRIL 2006


STAGE 2 - RENOVATE AND SELL OLDER HOUSE:

RENOVATE OTHER PROPERTY FOR SELLING - COMPLETED NOVEMBER 2008
HOUSE SOLD - FEBRUARY 10 2012


STAGE 3 - BUILD THE SECONDARY DWELLING, A TRANSPORTABLE CABIN:

CABIN ORDERED - MARCH 2010
CABIN DELIVERED - JULY 2010
MOVED INTO CABIN - SEPTEMBER 2010


STAGE 4 - BUILD PRIMARY DWELLING, THE MASTERTON "SIROCCO 7":


TENDERS, PLANS & CONTRACTS:
30.01.12 - SITE INSPECTION
06.02.12 - BUSH FIRE REPORT (BAL-29)
08.02.12 - DETAILS SENT TO SYDNEY FOR FIRST TENDER
27.02.12 - FIRST TENDER RECEIVED
07.03.12 - SECOND TENDER RECEIVED
12.03.12 - THIRD TENDER RECEIVED
13.03.12 - FOURTH TENDER RECEIVED
14.03.12 - PLAN PREP SIGNED AND PAID ($3.5K)
21.03.12 - POLITICAL CONTRIBUTIONS STATEMENT/AUTHORITY TO REFUND LEVY/NO ALLOWANCE SCHEDULE SIGNED
29.03.12 - CONTOUR SURVEY DONE
29.03.12 - BASIX COMPLETED
04.04.12 - 149 CERTIFICATE COMPLETED
10.04.12 - TENDER VARIATION
17.04.12 - RECEIVED AND SIGNED CUSTOM COLOUR SELECTION PACK
18.04.12 - FIRST DRAWN PLANS RECEIVED
02.05.12 - CURTAINS PURCHASED
09.05.12 - SECOND DRAWN PLANS RECEIVED
10.05.12 - PLANS SIGNED OFF / PRE-COLOUR CONSULT
29.05.12 - CONTRACTS SIGNED
30.05.12 - OSMS APPLICATION SUBMITTED & 5% DEPOSIT PAID
07.06.12 - OSMS APPROVED AND LODGED FOR CDC

SELECTIONS, APPROVALS & PRE-CONSTRUCTION:

16.06.12 - WET AREA FLOOR/WALL TILES & FLOOR SELECTIONS IN MITCHELL, A.C.T
18.06.12 - DEPOSIT PAID TO ACCENT FOR BAMBOO FLOORING
21.06.12 - COLOUR SELECTIONS APPOINTMENT
22.06.12 - CDC APPLICATION LODGED
22.06.12 - HANDED OVER TO PCC (PRE CONSTRUCTION CO-ORDINATOR)
25.06.12 - SENTINAL ALARM SELECTIONS COMPLETED
26.06.12 - AIR CON CONSULTATION
27.06.12 - AIR CON SIGNED OFF
28.06.12 - CDC APPROVED
02.07.12 - 1% SECTION 94EC PAID
04.07.12 - BLOCK CLEARED, READY FOR PEG-OUT
04.07.12 - NOTIFIED NEIGHBOURS OF CDC APPROVAL
05.07.12 - SITE PEG-OUT ORDERED
06.07.12 - COLOURS SIGNED OFF
11.07.12 - CONSTRUCTION PLANS SENT TO DRAFTING
11.07.12 - ELECTRICAL SELECTIONS  1st APPOINTMENT (VIA PHONE & EMAIL)
13.07.12 - ELECTRICAL SELECTIONS  2nd APPOINTMENT (VIA PHONE & EMAIL)
13.07.12 - SITE PEG-OUT COMPLETED
16.07.12 - ELECTRICAL SELECTIONS SIGNED OFF
25.07.12 - CONSTRUCTION PLANS SIGNED OFF
25.07.12 - FINAL TENDER SIGNED OFF
25.07.12 - VALIDATION SIGNED OFF

CONSTRUCTION (7 PROGRESS STAGES): PROGRESS STAGE 1 - SLAB:

26.07.12 - 20 DAY COUNTDOWN BEGINS
15.08.12 - WELCOME LETTER RECEIVED - MET SS OVER PHONE
16.08.12 - SEDIMENT CONTROL FENCE & TRADE WASTE AREA INSTALLED             
17.08.12 - PORT-A-LOO DELIVERED
17.08.12 - SITE SCRAPE BOOKED IN FOR THURSDAY 23rd AUGUST
18.08.12 - NEW SERVICES TRENCH STARTED
20.08.12 - NEW SERVICES TRENCH COMPLETED
21.08.12 - SITE SCRAPE, CUT & FILL STARTED EARLY
22.08.12 - NEW SERVICES LAID
25.08.12 - SITE SCRAPE, CUT & FILL FINISHED
27.08.12 - TEMPORARY PROTECTIVE FENCING INSTALLED
28.08.12 - PEERING & FORM-WORK STARTED (ISSUES WITH PEERING)
28.08.12 - SLABS & FOOTINGS INSPECTED (FAILED)
28.08.12 - OSMS REVISION SUBMITTED
29.08.12 - OSMS REVISION APPROVED
29.08.12 - UNDER-SLAB PLUMBING DONE
30.08.12 - COLLECTION WELLS HOLE DUG OUT
31.08.12 - COLLECTION WELLS INSTALLED
01.09.12 - TOP SOIL MOVED
05.09.12 - FILL REMOVED & TRENCH DUG FOR PIPEWORK
06.09.12 - COLLECTION WELLS PLUMBED IN & BACK FILLED (BY HAND)
07.09.12 - TANKS BACK FILLED (FINAL 10% - BY HAND)
11.09.12 - FORM-WORK & REO 90% COMPLETED. WAFFLE PODS COMPLETED
12.09.12 - FORM-WORK & REO COMPLETED
12.09.12 - SLABS & FOOTINGS INSPECTED (PASSED)
13.09.12 - SLAB POURED
17.09.12 - FIRST PROGRESS PAYMENT DONE
PROGRESS STAGE 1 COMPLETE.

PROGRESS STAGE 2 - FRAMES & TRUSSES:
18.09.12 - 10,000L WATER TANK DELIVERED
19.09.12 - EXTERNAL PLUMBING & DRAINAGE COMPLETED
19.09.12 - STORMWATER INSPECTED (PASSED)
24.09.12 - FRAMES AND ROOF TRUSSES DELIVERED
25.09.12 - SCAFFOLDING FOR BEAMS DONE
26.09.12 - FRAMES UP
27.09.12 - ROOF TRUSSES STARTED & WINDOWS DELIVERED
28.09.12 - MORE ROOF TRUSS WORK
02.10.12 - ROOF TRUSSES DONE - WINDOWS INSTALLED
02.10.12 - SECOND PROGRESS PAYMENT DONE
PROGRESS STAGE 2 COMPLETE.

PROGRESS STAGE 3 - BRICKS:
03.10.12 - EXTERNAL DOOR FRAMES INSTALLED - FRAME/TRUSSES FINISHED OFF
04.10.12 - BRICKS DELIVERED - INTERNAL PLUMBING STARTED
04.10.12 - FRAMES INSPECTED (PASSED)
05.10.12 - INTERNAL PLUMBING FINISHED
06.10.12 - SAND FOR BRICKLAYING DELIVERED
08.10.12 - CEMENT & TIES DELIVERED - INTERNAL PLUMBING INSPECTED
10.10.12 - BRICKS STARTED (1st COURSE) - RANGEHOOD DUCTING INSTALLED
11.10.12 - ENVIROSEAL WRAP INSTALLED - GRANITEGARD STARTED
15.10.12 - MORE BRICKWORK - ALFRESCO STACKER DOOR FRAME INSTALLED
16.10.12 - MORE BRICKWORK - GRANITEGARD FINISHED BY ME
17.10.12 - MORE BRICKWORK
18.10.12 - MORE BRICKWORK (2/3 COMPLETE) - EXTERNAL TAPS PLUMBED IN
22.10.12 - MORE BRICKWORK
23.10.12 - MORE BRICKWORK
24.10.12 - BRICKWORK COMPLETE
25.10.12 - GUTTERS & FASCIAS DELIVERED
26.10.12 - SCAFFOLDING FOR BEAMS REMOVED
26.10.12 - THIRD PROGRESS PAYMENT DONE
PROGRESS STAGE 3 COMPLETE.

PROGRESS STAGE 4 - ROOF:
30.10.12 - FASCIAS AND GUTTERS INSTALLED
30.10.12 - ROOF TILES DELIVERED
31.10.12 - ROOF SAFETY RAIL AND SARKING & BATTENS INSTALLED
01.11.12 - ROOF TILES STARTED
02.11.12 - MORE ROOF WORK (AROUND 90%) DONE - WHIRLYBIRDS INSTALLED
05.11.12 - BRICKS CLEANED
06.11.12 - ROOF TILE RIDGE CAPS ON - SENTINAL CABLING ROUGH IN DONE
07.11.12 - ELECTRICAL ROUGH IN DONE
08.11.12 - EAVES AND CAVITY SLIDING DOORS MATERIAL DELIVERED
09.11.12 - AIR CON DUCTING & FAN COIL UNIT INSTALLED IN CEILING
12.11.12 - FRAME TIDY UP - SLIDING DOOR CAVITIES & VANITY BASES INSTALLED
12.11.12 - INSULATION DELIVERED
12.11.12 - FOURTH PROGRESS PAYMENT DONE
13.11.12 - EAVES INSTALLED - WALL INSULATION DONE & CEILING STARTED
13.11.12 - GYPROCK DELIVERED
PROGRESS STAGE 4 COMPLETE.

PROGRESS STAGE 5 - LOCK-UP:
14.11.12 - GYPROCK STARTED - ROOF SAFETY RAIL REMOVED
15.11.12 - MORE GYPROCKING. WALLS PRACTICALLY DONE. CEILINGS STARTED
16.11.12 - WALLS & CEILINGS DONE - GYPROCK FINISHED
19.11.12 - STINK-PIPES FINISHED AND WATERTIGHT
21.11.12 - RUBBLE REMOVED
23.11.12 - PLASTERING STARTED
26.11.12 - MORE PLASTERING 
27.11.12 - MORE PLASTERING - CORNICES STARTED
28.11.12 - CORNICES 90% DONE - EX. ENSUITE, BATHROOM & KITCHEN
29.11.12 - LAUNDRY, BATHROOM & ENSUITE FLOOR & WALL TILES DELIVERED
30.11.12 - LAUNDRY, BATHROOM & ENSUITE WATER PROOFING DONE
30.11.12 - 60% OF DOORS & ARCHITRAVE / SKIRTING TIMBER(MDF) DELIVERED  
03.12.12 - SAND & CEMENT DELIVERED FOR FLOOR TILE BASES
03.12.12 - FRONT, LAUNDRY & INTERNAL ACCESS DOORS ON. LOCK-UP STAGE
04.12.12 - MORE DOOR & ARCHITRAVE WORK
04.12.12 - WATERPROOFING INSPECTED (PASSED)
05.12.12 - MORE DOOR & ARCHITRAVE WORK
06.12.12 - MORE DOOR & ARCHITRAVES - FIFTH PROGRESS PAYMENT DONE
PROGRESS STAGE 5 COMPLETE.

PROGRESS STAGE 6 - PRACTICAL COMPLETION:
10.12.12 - ALL CUPBOARD DOORS, SPA BATH & LAUNDRY TUB DELIVERED
11.12.12 - ALL REMAINING DOORS, ARCHITRAVES & SKIRTING DONE
12.12.12 - KITCHEN, BATHROOM & ENSUITE CUPBOARDS DELIVERED (@10pm!!) 
13.12.12 - DOWNPIPES INSTALLED
13.12.12 - KITCHEN & ENSUITE CUPBOARDS INSTALLED
13.12.12 - SPA BATH BASE & LAUNDRY, BATHROOM & ENSUITE BASES DONE
14.12.12 - FLOOR TILES DONE
15.12.12 - WALL TILES DONE IN MAIN BATHROOM  
16.12.12 - WALL TILES DONE IN ENSUITE & LAUNDRY 
17.12.12 - MOST OF THE WALL & FLOOR TILES GROUTED
19.12.12 - FRONT DOOR SIDELIGHT & OTHER TIMBER DELIVERED
20.12.12 - XMAS SHUTDOWN COMMENCED
11.01.13 - XMAS SHUTDOWN FINISHED - STONE BENCHES, SINK & VANITIES INSTALLED
17.01.13 - FRONT DOOR SIDELIGHT + FINAL SKIRTING & ARCHITRAVES INSTALLED.
21.01.13 - CORNICES COMPLETED (ENSUITE, BATHROOM & KITCHEN)
22.01.13 - LAUNDRY, ENSUITE & BATHROOM TILING COMPLETED
23.01.13 - PAINTING PREP STARTED - TOILETS & HOT WATER SYSTEM DELIVERED
24.01.13 - 1ST COAT OF EXTERNAL PAINTING DONE
25.01.13 - EXTERNAL PAINTING DONE - CANOPY/RANGEHOOD DELIVERED
28.01.13 - RANGE-HOOD TRIAL FITTED FOR SPLASH-BACK MEASUREMENTS
28.01.13 - INTERNAL PAINTING STARTED
29.01.13 - INTERNAL PAINTING - WALLS UNDERCOATED & SOME TOP COAT
30.01.13 - INTERNAL PAINTING - FIRST TOP-COAT AND CEILINGS DONE
31.01.13 - INTERNAL PAINTING - DOORS UNDERCOATED - CUTTING IN STARTED
31.01.13 - SPLASH-BACK MEASURED FOR FITTING
01.02.13 - INTERNAL PAINTING - CUTTING IN 1ST TOP COAT
02.02.13 - INTERNAL PAINTING - CUTTING IN 2ND TOP COAT + ABOVE GARAGE
03.02.13 - INTERNAL PAINTING - DOORS GLOSSED
04.02.13 - INTERNAL PAINTING - 90% ARCHITRAVES & SKIRTING GLOSSED
04.02.13 - DOOR HANDLES AND TOWEL RAILS ETC DELIVERED 
05.02.13 - INTERNAL PAINTING COMPLETED
06.02.13 - PLUMBING FIT-OUT 95% DONE
07.02.13 - CUPBOARD SHELVING INSTALLED - GARAGE DOORS INSTALLED
07.02.13 - PLUMBING FIT-OUT DONE- SPA INSTALLED - ELECTRICAL FIT-OUT DONE
08.02.13 - ROOF INSULATION, SENTINEL + SHOWER SCREENS/MIRRORS DONE
09.02.13 - DOOR FURNITURE & BATHROOM/ENSUITE ACCESSORIES INSTALLED
11.02.13 - BRICKWORK REPAIRED - QUICK INTERNAL CLEAN
12.02.13 - AIR CON UNIT & DUCTS INSTALLED - SLIDING WINDOWS & DOORS SERVICED
13.02.13 - BAMBOO FLOORING INSTALLED
14.02.13 - SCREEN DOORS & WINDOW SCREENS INSTALLED - PORT-A-LOO REMOVED
18.02.13 - SKIRTING BACK ON & PAINTED + FINAL PAINT TOUCH-UPS DONE
19.02.13 - FULL SITE CLEAN - FULL INTERNAL CLEAN
19.02.13 - OCCUPATION CERTIFICATE INSPECTION (FAILED) - HOUSE INCOMPLETE
20.02.13 - FINAL PLUMBING & DRAINAGE INSPECTION - PASSED (PENDING TANK)
21.02.13 - PRACTICAL COMPLETION INSPECTION
21.02.13 - SIXTH PROGRESS PAYMENT DONE
PROGRESS STAGE 6 COMPLETE.

PROGRESS STAGE 7 - FINAL.
21.02.13 - SEVENTH PROGRESS PAYMENT DONE
22.02.13 - TEMPORARY PROTECTIVE FENCING REMOVED
25.02.13 - HANDOVER & KEYS
26.02.13 - MIRROR SPLASH-BACK INSTALLED
27.02.13 - FINAL PAINT TOUCH-UPS DONE - DOOR STOPS DONE
28.02.13 - OVEN & DISHWASHER DELIVERED
01.03.13 - OVEN, RANGEHOOD, DISHWASHER & HOT WATER CONTROLLERS INSTALLED
MASTERTON HAVE NOW FINISHED - 90 DAY MAINTENANCE CHECK IS NEXT.


POST HANDOVER (ITEMS NOT DONE WITH MASTERTON):
25.02.13 - CURTAINS INSTALLED - LIGHT FITTINGS DONE - STARTED MOVING IN
26.02.13 - CARPETS INSTALLED
26.02.13 - MOVED IN
01.03.13 - PHONE CONNECTED
16.03.13 - POOL TABLE FINALLY IN - STARTED HANGING PICTURES ETC
17.03.13 - BLINDS INSTALLED IN KITCHEN, ENSUITE AND MAIN BATHROOM
10.04.13 - ANTENNA INSTALLED
13.05.13 - RAINWATER RE-USE WATER TANK CONNECTED
17.05.13 - GUTTER GUARD INSTALLED
21.05.13 - BLINDS INSTALLED IN FRONT BEDROOMS AND HOME THEATRE
05.06.13 - RAINWATER RE-USE PUMP CONNECTED
24.06.13 - 90 DAY MAINTENANCE INSPECTION CARRIED OUT - FEW ISSUES RAISED
26.07.13 - INVISI-MESH SECURITY SCREEN DOOR INSTALLED (FRONT DOOR)
20.08.13 - ALL MAINTENANCE WORK COMPLETED BY MASTERTON
25.08.13 - DRIVEWAY SCRAPED
30.09.13 - DRIVEWAY FORM-WORK STARTED
02.10.13 - DRIVEWAY FORM-WORK FINISHED
03.10.13 - DRIVEWAY POURED

1 comment:

  1. Prefabricated timber wall frames
    offer many benefits including:

    A reduction in costs

    Improved energy efficnency

    Precision engineered to Austrlian standards using
    Engineering software

    More sustainable / environmentally friendly

    Prefabricated timber roof trusses
    have been part of Australian building practices for over 30 years. Builders who
    regularly use roof trusses claim the following benefits:

    Cost effective

    Piece of mind for building authorities and certifying
    engineers

    Design flexibility

    Ease of installation

    Here are other services Sydney Frame and Truss
    2. Frame and Truss 3. Frames and Trusses 4. Truss and Frames 5. Trusses and
    Frames 6. prefabricated frames and flooring.

    ReplyDelete